In the Penza region, the contractor was blacklisted for disrupting the improvement of yards
In the Penza region, the contractor did not perform work on the improvement of yards of apartment buildings in the prescribed period. Violation of the terms of the municipal contract became the basis for proceedings in the antimonopoly authority.

In the Penza region, the contractor did not perform work on the improvement of yards of apartment buildings in the prescribed period. Violation of the terms of the municipal contract became the basis for proceedings in the antimonopoly authority.
The contract between the municipal administration and the contractor was concluded on May 11, 2026. According to the approved schedule, the improvement work was to be completed by August 30.
However, by the due date, the organization has not fulfilled all contractual obligations. As a result, on August 31, the customer decided to unilaterally refuse to perform the contract.
During the consideration of the case, the representative of the company explained that part of the work was still carried out. To complete the improvement, it remained to lay asphalt concrete coating, but it was allegedly not possible to do this in time due to the lack of the necessary mixture from the supplier.
At the same time, the contractor did not submit documents that would confirm the objective impossibility of completing the work both on time and after its expiration.
In addition, it turned out that during the same period, the company performed similar work under other contracts. According to the antimonopoly authority, this indicates that the problem with the supply of asphalt could be overcome, but the contractor preferred obligations to other customers.
Having studied the submitted materials and the circumstances of the case, the inspection of the regional department of the FAS concluded that there are grounds for including information about the company in the register of unfair suppliers.