In the Leningrad region, the energy of the future is formed. Governor Drozdenko spoke about the construction of new power units at LNPP
Governor Alexander Drozdenko spoke about the construction of new power units at the Leningrad NPP. “Forming the energy of the future,” he said.
Governor Alexander Drozdenko spoke about the construction of new power units at the Leningrad NPP. “Forming the energy of the future,” he said.
Now the nuclear power plant is in full swing construction of two new power units with VVER-1200 reactors - these are units 7 and 8. They should become key projects that will ensure the energy future of the region.
Currently, nuclear islands of power units are being built there. They will be the main technological process responsible for generating electricity. The facility employs 2,000 people, and in the new year there will be even more, up to 5,000.
At the third power unit of LNPP-2, the installation of the most important security system – “melting traps” – was completed. Concrete construction of the turbine building also continues there.
At the fourth power unit, the reactor shaft is being equipped, elements of the “melting trap” are being mounted and the protective shells of the reactor building are being erected.
The governor noted that passive safety systems were introduced at all new power units. They can work without human intervention and even without external power supply. Also in case of emergency situations, a double protective shell should provide additional protection.
The Leningrad NPP today covers about 35 percent of the electricity needs of the North-West region. The new power units with a capacity of 1,200 MW each will further strengthen the energy potential. And for decades to come.