In school No36 Cheboksar updated 40% of the roof and almost completed the facade
In school No36 Cheboksary continues major repairs

At school No. 36, Cheboksary continues major repairs. The main works on several floors have already been completed, now the contractor focuses on interior decoration, roofing and landscaping.
On the roof, the old coating, screed and ceramsite layer are dismantled, slopes are formed to drain water. In parallel, lay the insulation and mount the membrane coating.
To date, about 40% of the roof has been updated. Demolition and preparatory work continues on the remaining area.
On the second, third and fourth floors, the bulk of the work is now completed. Painting and tile work continues on the first floor. At the same time, the contractor updates the entrance group and arranges pavement.
The readiness of the facade is about 95%. It remains to complete separate sections near the doorways.
The progress of the overhaul is controlled by the Republican service of the single customer of the Ministry of Construction of Chuvashia. Specialists check the quality of work, compliance with construction technologies and the implementation of the remaining stages.