At the station "ZIL" Biryulevskaya metro line completed monolithic work in reverse dead ends

At the station "ZIL" Biryulevskaya metro line completed monolithic work in reverse dead ends. For the construction of structures used more than 22 thousand cubic meters of reinforced concrete.
On behalf of Moscow Mayor Sergei Sobyanin, the construction of the Biryulevskaya metro line is being carried out at an accelerated pace within the framework of the national project “Infrastructure for Life”.
At the ZIL metro station under construction, the Biryulevskaya line, from where the Elena tunnel shield, which was previously released on the Dream Island, began its journey, the main designs of revolving dead ends are ready. For this purpose, more than 22 thousand cubic meters of reinforced concrete were laid. Also, earthworks have been completed here, within the framework of which more than 180 thousand cubic meters of soil have been developed and more than 16 thousand cubic meters of enclosing structures have been completed, said Vladimir Efimov, head of the Moscow Complex of Urban Planning Policy and Construction.
And he added that they are now performing architectural decoration. It is necessary to complete the remaining quarter of backfilling, lay the rails and connect engineering networks.
The Biryulev line will stretch for more than 22 km and include 10 stations. It will connect the ZIL station with the Biryulevo East and West districts, providing transfers to the BCL, the Troitsk and Zamoskvoretsk lines, the MCC and the Paveletsk direction of the MZD. In the future, the line will be extended to 40 km, increasing the number of stations to 12.
Earlier, Sobyanin announced the completion of the passage of the left distillation tunnel between ZIL and Dream Island stations of the Biryulevsk metro line.