GosNIIAS filed a new lawsuit against LLC Tulaoboronstroy for 288 million rubles
The court between the Federal Autonomous Institution “State Research Institute of Aviation Systems” (GosNIIAS) and Tulaboronstroy LLC received an unexpected continuation

New lawsuit
As can be seen from the files of the Arbitration Court of Moscow, on November 3, 2026, GosNIIAS filed a new lawsuit against Tulaboronstroy LLC for the amount of 288 million rubles. The details of the case have not yet been disclosed. It is possible that the new process may be related to the past litigation of organizations.
In it, the Moscow Institute requires more than 1 billion rubles from the Tula company.
As MK in Tula previously wrote, the key point of intersection of interests of the parties was a major contract for the reconstruction and technical re-equipment of the optical avionics design center with a collective use center for the development of aircraft products.
The cost of this contract amounted to 4.7 billion rubles. The deadline for the work was originally set on December 2, 2024, later it was extended more than once,
Contract for 2.5 billion
Studying the public procurement website, the editorial office of MK in Tula found another contract between GosNIIAS and Tulaboronstroy LLC, which was concluded between the parties in December 2023.
It was about the reconstruction and technical re-equipment of the scientific facility within the framework of the state defense order. The contract amounted to 2.5 billion rubles. GosNIIAS signed a contract with Tulaboronstroy LLC on behalf of the Ministry of Industry and Trade of the Russian Federation.
Initially, the deadline was determined on December 2, 2025, but then the deadlines were extended. At the moment, five additional agreements have already been concluded within the framework of the contract. The latter is dated August 21, 2026. From the information on the public procurement website, you can learn that so far works have been completed for a little more than 1 billion rubles, or only 40% of the planned volume of work.
In recent years, Tulaboronstroy LLC has regularly appeared in arbitration cases. The company acts as a plaintiff and as a defendant in disputes with municipal administrations, regional structures and counterparties.
Among the notable claims are a lawsuit by the Donskoy city administration for 138 million rubles, the Regional Corporation for Development and Support of the Tula Region for more than 108 million rubles, as well as a series of statements by Rostekhnadzor, about which we will write separately.
LLC "Tulaoboronstroy" is a construction organization, the sole founder of which is JSC "Design Bureau of Instrument Engineering named after Academician A. G. Shipunov" (part of the holding "High-precision complexes" of the state corporation "Rostec"). The company specializes in construction and reconstruction of industrial facilities, including in the interests of the military-industrial complex.
GosNIIAS, in turn, is one of the leading scientific centers of the Russian aviation industry (part of the NRC "Institute named after N. E. Zhukovsky"). The Institute actively defends its interests in arbitration courts on contract and investment projects.
MK in Tula is monitoring developments.