Readiness of kindergarten in Yanino-1 reached 65 percent
In Yanino-1, the construction of a kindergarten for 240 places on Tsvetnoy Boulevard is being completed. Its readiness was estimated at 65 percent, the press service of the regional construction committee reported.

In Yanino-1, the construction of a kindergarten for 240 places on Tsvetnoy Boulevard is being completed. Its readiness was estimated at 65 percent, the press service of the regional construction committee reported.
The frame of the building has already been erected, the roof and window blocks have been installed. The facade work was completed by 90%. Currently, the contractor has started interior decoration, installation of engineering networks and improvement of the territory. It is planned that the new institution will be ready for operation in the first quarter of 2027.
In the kindergarten will be formed 12 groups, including two nurseries. As well as sports and music halls, game and training areas. Interiors were developed in conjunction with child psychologists: blue is designed for classes, yellow for games, and green for recreation.
Earlier, “MK in Leningrad region” said that the kindergarten on School street in Vsevolozhsk built about a third.