Readiness of Nekrasovsky bridge in Vologda reached 95%
Construction of the Nekrasovsky bridge in the regional capital has reached the final stage

The construction of the Nekrasovsky bridge in the regional capital has reached the final stage. The readiness of the object is more than 95%. At the moment, 145 specialists and 23 units of equipment are involved at the site. Work goes on overpasses in the alignment of Burmaginy Street and on the overpass itself.
The first overpass completed the concrete monolithic stop and began the installation of the barrier fence. On the second overpass, the installation of the fence is completed. The bridge continues work on the channel part and the second stage of installation of the bridge collector.
The upper layer of asphalt is laid on an area of 4.5 thousand square meters. The sidewalks are paved on an area of 8.9 thousand square meters. Barrier fences are being installed.
Nekrasovsky bridge will become part of the future Small transport ring of Vologda. Its creation was supported by the president.