Capremont in Kursk schools and kindergartens - under the control of the Governor
In Kursk, the overhaul of educational institutions is in full swing. Seven facilities are being updated as part of the national projects “Youth and Children” and “Family”, and Governor Alexander Khinshtein keeps this process under personal control.

In Kursk, the overhaul of educational institutions is in full swing. Seven facilities are being updated as part of the national projects “Youth and Children” and “Family”, and Governor Alexander Khinshtein keeps this process under personal control.
The Education Committee on behalf of the head of the city Yevgeny Maslov arranges regular inspections. Today, the work was assessed by the Chairman of the Committee Dmitry Ivanov.
School 31. The facility employs 30-35 people: plastering walls, mounting ceilings, waiting for batteries for heating. There were no delays - Dmitry Ivanov warned about the inadmissibility of disrupting the terms under the contract.
School 14. The facade is almost ready, everything is not smooth inside. The heating device goes, but there is a risk of not having time to start the heating season. There are 50 people working on the site.
Kindergarten 128. A contractor who already had complaints. Now 11-12 people work: wallpaper in groups is glued, ceilings are mounted, heating will be launched in the coming days. The contract term is December 1, but the pace is low, so the contractor is monitored especially closely.
School 28. Finish is close, everything will be completed in the coming weeks. There are 12 people at the facility.
Kindergarten 40. 11 people work here. In the area of attention of the roof, facade, electricity, water, heating and finishing. The roof is ready, the first floor is plastered, the second one is patted. The facade - next week, the heating will start early next week.
Kindergarten 127. The roof is ready, the facade is almost finished. There are 21 people at the facility. The garden is ready for heating.
School 27. The main thing is inside: the facade is ready, the details remain. Three heating units are waiting to start. Tiles are laid on stairs and in corridors, the walls in the offices are painted. There are 50 people at the facility. Repairs are ongoing - specialists are doing everything to meet the deadline.