Likhachev spoke about the first kilowatt-hours of the Rooppur NPP
The head of Rosatom Alexei Likhachev announced the issuance of the first electricity of the Rooppur NPP to the Bangladesh network on November 17

The head of Rosatom, Alexei Likhachev, announced the issuance of the first electricity to the Rooppur NPP in the Bangladesh network on November 17. The first power unit of the plant was connected to the national power grid; for the country, this is the beginning of its own nuclear generation.
Alexey Likhachev spoke about the reaction of the partners after a conversation with the project manager from Atomstroyexport. “This is a long-term dream of the Bengali people,” said Alexey Likhachev. He noted that the parties went to the result together for many years.
The first connection took place at 15:15 local time. When synchronized, the power of the reactor plant was 40% of the nominal, the generator - 370 MW. Such indicators are recorded precisely when the block is synchronized with the network, until all launch stages are completed.
The unit was brought to a minimum controlled power level in mid-October. The reactor then began a self-sustaining controlled chain reaction. Power was increased gradually until it was possible to start the turbine and transmit electricity through the generator.
Likhachev connects the development of nuclear energy in Bangladesh with technological and scientific development. According to the head of Rosatom, now the country gets access to advanced technologies, and the project contributes to the development of the engineering school and research. Connection to the network indicates an important but intermediate result.
Ahead is the further development of capacity during pilot-industrial operation, after which commercial will begin. The station is located 160 km from Dhaka and includes two units with VVER-1200 Generation III+ reactors. The total design capacity of both units is 2400 MW.