Likhachev said: at the nuclear power plant “Akkuyu” began running the block
At the first power unit of the Akkuyu NPP, a cold-hot run-in began, Rosatom Director General Alexei Likhachev said

At the first power unit of the Akkuyu NPP, a cold-hot run-in began, Rosatom CEO Alexei Likhachev said. The Turkish regulator allowed the tests necessary to prepare the unit for physical launch.
The run-in, which Likhachev says, will allow you to check both circuits at the design temperature and pressure. The tests cover the strength of pipelines and equipment, the level of vibration and the operation of electrical equipment. Another part of the program is testing the safety, control and protection systems of the reactor; the actions of the personnel will be checked.
“This means that we are literally no longer in step, but halfway to the physical launch,” said Alexei Likhachev. During the run-in in the active zone will be simulators of fuel assemblies. The plant itself will provide power to an external source; uranium fuel is not loaded at this stage.
Before the physical launch, the proximity of which Likhachev spoke, experts will conduct an audit of the main and auxiliary equipment. It must confirm the compliance of the equipment with design requirements and the readiness of the unit for physical start-up. The Turkish regulator will issue a separate permit before launching operations. For the first time, uranium fuel will be in the reactor during the physical start-up phase.
The Rosatom station is being built in Mersin province on the Mediterranean coast. Akkuyu will be Turkey’s first nuclear power plant. The capacity of each unit is 1200 MW. Once all units reach full capacity, the plant is expected to provide about 10% of the country’s electricity needs.