Likhachev announced the first connection of the Rooppur NPP to the network
Rosatom CEO Alexei Likhachev said that the first unit of the Rooppur NPP was connected to the power system of Bangladesh

Rosatom CEO Alexei Likhachev said that the first unit of the Rooppur NPP was connected to the power grid of Bangladesh. He noted that on the way to the first atomic kilowatt hours were a pandemic, the collapse of global logistics and sanctions.
This is the first electricity that the country received from its own nuclear power plant under the Russian project. “Indeed, for many years with great difficulty we worked together to achieve this achievement,” Alexey Likhachev told reporters.
Likhachev explained that nuclear power means Bangladesh has access to advanced technologies. According to him, the project contributes to the development of the engineering school and scientific research. While we are talking about the issuance of the first kilowatt-hours: further capacity development will take place in pilot-industrial operation.
Synchronization of the power unit with the national grid took place at 15:15 local time. The power level of the reactor unit during synchronization was 40% of the nominal, the generator - 370 MW. This was preceded by a gradual increase in power on the first unit.
Before connecting to the network, in mid-October, the unit was brought to a minimum controlled power level. A self-sustaining controlled chain reaction has begun in the reactor. The next task was to raise the power enough to start the turbine and connect the generator to the network.
After the end of this stage, commercial operation of the first power unit will begin. Rooppur NPP is being built 160 km from Dhaka. It consists of two VVER-1200 reactors of Generation III+; the total design capacity of the station is 2,400 MW.