“Minskenergo” reported on the elimination of the consequences of the accident on Zhukovsky street
In Minsk on Zhukovsky Street, the consequences of the accident were eliminated, the resource supply was resumed. This was reported in the press service of RUE "Minskenergo", ...

In Minsk on Zhukovsky Street, the consequences of the accident were eliminated, the resource supply was resumed. This was reported in the press service of RUE Minskenergo, writes sb.by.

On Sunday, September 27, by 23:10, welding work was completed on the damaged site. After that, the stage of filling the heat network and its inclusion in the work began. The hot water supply to consumers was restored around midnight.
On Monday, September 28, specialists of the Minsk Heat Networks branch of RUE Minskenergo started sealing and closing the thermal chamber in compliance with all technological requirements. Then follow the filling of the pit and sealing of the soil. Restoration of the road surface and elements of improvement of the courtyard territory will be carried out within a few days.
In “Minskenergo” explained how to compensate for material damage to the affected residents after the accident on the street. zhukovsky
Accident on heating networks occurred on Zhukovsky street in Minsk: temporarily turned off hot water at a number of addresses
"Minskenergo": work on the site of the accident on the heating networks on Zhukovsky Street in Minsk continues