"Novgorod Vodokanal" told about the reconstruction of the left-bank treatment plants
On the left-bank sewage treatment facilities of the Novgorod Vodokanal, work is boiling

On the left-bank sewage treatment facilities of the Novgorod Vodokanal, work is in full swing. There is a large-scale reconstruction, which was necessary for a very long time: there was no overhaul from the very foundation of the facilities in 1972, the press service of JSC Novgorod Vodokanal reported.
Eighty people and five pieces of equipment are involved in the process. Builders lay trays on pipelines with a diameter of 250 and 400 millimeters. In the premises of the First Reagent Farm, the premises remove old plaster, strengthen the walls with a grid, ground the surfaces and install accurate measuring devices in the water supply chamber. In the second building at the same time mount a modern ventilation system.
Do not forget about the outside of the buildings. On the main building, cracks on the facade are repaired and a protective pavement is equipped to protect the foundation from moisture.