New pumping station for 965 buildings to be built in Novosibirsk by 2029
In Novosibirsk will replace the pumping station No. 1 near the October bridge, which provides heat to hundreds of buildings

The new PNS-1 will pump coolant from CHPP-2 for 965 buildings in the Central, Railway and October districts. Its service area will include 407 apartment buildings, where more than 55.5 thousand people live, 30 children's institutions and 18 medical organizations.
Now SGC conducts design and survey work. Construction is planned for 2027-2028, and the launch of the facility - for 2029. In 2027, they will also begin to purchase basic equipment and reconstruct the adjacent heating system. The diameter of the pipes will be increased to increase the capacity of the system.
The capacity of the new station will grow by 50% - from the current 5 thousand to 7.5 thousand cubic meters per hour. This will increase the capacity of the heat system and ensure the connection of new consumers as the city develops. The additional reserve will be 200 Gcal / h.
The station will install pumping equipment on the supply and return pipelines: four units in each direction. Three pumps will be working, one - backup. The capacity of each will be 2.5 thousand cubic meters per hour at a pressure of 80 meters.
In addition, the project provides for the construction of new thermal chambers with regulating valves and the laying of about 500 meters of additional heat networks with a diameter of 800 and 1000 mm.
Pumping stations ensure the circulation of the coolant between the CHP and consumers, maintaining the necessary pressure in the system. There are 11 such facilities in Novosibirsk. SGC is implementing its renewal program for the fourth year. In 2026, three stations on the right bank underwent modernization, previously work was carried out on the left bank facilities.
Earlier, "MK in Novosibirsk" reported that the lake Kvadratka became bright green due to leakage on the heating networks.