From Kursk to Tver region: road workers " Terra" told about the progress of work
Specialized teams of Terra Company continue to fulfill state contracts for the construction, repair and maintenance of roads in several regions of Russia

Specialized teams of Terra continue to fulfill state contracts for the construction, repair and maintenance of roads in several regions of Russia. According to the report, work is carried out at facilities in the Kursk, Tver and Leningrad regions. The total length of the sections covered by the contracts exceeds 130 km.
Most of the contracts are in the Kursk region. In the Soviet district on the road "Kursk-Kastornoe" work was carried out on the site length of 9 km.
In the Kursk district, the road “Kursk – Ponyri” is being repaired, the section “Crimea – Dryablovo – the border of the October district”, “Crimea – Dronyaevo”, “Kursk – Ponyri – Bukreevka” and the entrance to the regional clinical anti-tuberculosis clinic.
At the facility "Crimea - Dryablovo - the border of the Oktyabrsky district" the development of soil by an excavator, the pouring of berms under signs and a concrete preparation device were carried out.
In Kastorensky district on the road "Kursk - Borisoglebsk - Kastornoye - border of the Lipetsk region - Pogozhevo" bottling of a bitumen emulsion and a coating device from ShchMA-16 on the square, as well as a seam joint device were made. On the section of km 23+000 - km 32+850 filled support wall, installation of side stones and roadside layout.
In the Shchigrovsky district on the road "Kursk-Kastornoe" works cover 6,452 km.
On the road "Kursk - Borisoglebsk - Kshensky - the border of the Lipetsk region - Kshen - Panskoye" made a barrier fence, dismantling and installation of side stones, strengthening the roadside. At the site "Kshen - Panskoye - Mansurovo" work continues.
In the Tver region under contracts repaired roads "Ulyanovo - Belavino", "Moscow - Riga - Nikolo-Pustin", "Glebovo - Dunilovo" and the entrance to the village of Konkovo in Zubtsov, Rzhev and Staritsky districts.
In addition, on the road R-132 "Golden ring" arranged layers of wear on sections of km 1147+800 - km 1162+753 and km 1198+545 - km 1222+963. Work completed.
In the Kingisepp district of the Leningrad region, an access road is being built to the landfill of solid household and certain types of industrial waste. The length of the site is more than 3 km, the completion date is October 31, 2027.
Among the major contracts are the reconstruction of the road R-298 "Kursk - Voronezh - road R-22 "Caspian" - Kshensky - M-4 "Don" and the construction of the South-East bypass of Kursk on a section of km 0+000 - km 12+000.
Terra noted that all current work is carried out in accordance with schedules and is under the control of specialized services.