Fully open traffic on the Myzinsky bridge can in early December
Traffic on the Myzinsky bridge is going to open in full in the first days of December

Traffic on the Myzinsky Bridge overpass is going to open in full in the first days of December. Such information at a meeting of the transport committee of the city Duma on November 20 was voiced by Ilya Kurapov, First Deputy Head of the Moscow State University “Main Department for Construction and Repair of Metro, Bridges and Road Networks in Nizhny Novgorod”.
Recall: at the end of October due to repair work on the entrances to the Myzinsky bridge began to occur congestion length of several kilometers. City Duma deputy Maria Kuznetsova said that recently drivers had to stand in traffic for about five hours. She asked when the repairs would be finished.
“The pace of work of the contractor can be assessed positively,” said Ilya Kurapov.
According to him, a daily schedule of work was agreed with the contractor. Now the contractor is preparing the sidewalk, and on November 21 - will concrete it. On November 23-24, work is planned on the arrangement of asphalt concrete layers on the sidewalk, then the device of three deformation seams will begin.
“It is planned to launch a third phase by the end of next week. There, probably, a week will remain a slight restriction of movement for the installation of axial railing. It is planned to launch traffic on all lanes in early December. We see that by this time the contractor is going, said the first deputy director of GUMMid.
He explained that the contract work should be completed on December 5, but it is important to take into account the weather conditions.