It will optimize the logistics of utility equipment. In Minsk built the third snowmelting station
A third snow smelting station was built in the Belarusian capital. This is reported on the website of RUE "Belstroycenter", writes sb.by. Photo: RUP ...

A third snow smelting station was built in the Belarusian capital. This is reported on the website of RUE "Belstroycenter", writes sb.by.

The structure is located at the intersection of the Moscow Ring Road with Timiryazev Street, near Zhdanovichi. The customer was UE “Minskvodokanal”, the general contractor is a branch of “SU-13” of OJSC “Stroytrest No. 4”. General construction management and technical supervision were provided by Belstroycenter employees.
The station will make it possible to optimize the logistics of municipal equipment: trucks from Frunze and Central districts will no longer need to carry snow to the other end of the city in Shabani. The builders met the winter: the object was completed ahead of schedule - five months instead of ten.
The heart of the object is an underground reinforced concrete chamber with a depth of 6 m and a volume of more than 2.5 thousand cubic meters. For uninterrupted operation, 4 grilles-crushers are provided at the station, which makes it possible to simultaneously unload 3-4 machines with a cargo volume of 20 cubic meters. The incoming snow mass is crushed by crushers and melted due to the warm waters of the city sewerage. A mixture of melted snow and effluent passes through the sandstone, where sand and suspensions settle and precipitate.
Floating debris is delayed by containers, which are lifted by a crane and taken to the landfill. A separate partition was installed to capture petroleum products. After cleaning from sand and large debris, melt water is sent to the Minsk treatment plant. The daily productivity of the snowmelting point is about 5 thousand cubic meters.
For maintenance, control and management built auxiliary structures: remote, workshop and automobile scales.
The object was built in difficult hydrogeological conditions - at a high level of groundwater and on a cramped site. In a couple of months, the station will be fully operational.