The overhaul of the kindergarten in the village of Pinega continues
14 people work at the facility

There are 14 people working at the facility. Special attention is paid to engineering systems. Heating is already partially functional, 18 radiators are working, and today the system will be launched throughout the building.
Electricians have completed the installation of lighting on the second floor and in the basement, on the first floor the fixtures are installed at 70 percent.
The interior decoration continues. The walls are prepared for painting, half of the second floor has already been painted. The floor leveling is complete throughout the building.
The tile is laid on the walls and on the floor, only the final work on the thresholds remains. The ceilings remained to be completed in the hall and in four small rooms.
In parallel, the roofing work began. Material has already been delivered to the facility. Masters roll metal and prepare false roof on a special machine. They will soon begin laying on the roof.