Renovation of schools No. 40 and 33 in Bryansk is behind schedule due to a shortage of workers
School No. 40 began repairs in April.

The head of the administration of Bryansk Alexander Makarov demanded to increase the number of workers at the overhaul facilities of schools No. 40 and 33. Due to a shortage of builders, contractors are behind schedule.
On November 11, Makarov checked the progress of work in both educational institutions. The buildings were built in the postwar years, and for all the time of their existence, major renovations of this scale were not carried out. During the repair, it is necessary to eliminate problems with worn communications and structures.
School No. 40 began repairs in April. A new roof has already been laid here, the installation of the roof of the sports hall and the insulation of the facade of the old building are continuing. Inside, the first and second floors are repaired, doors are installed and furniture is imported. Also equip the pavement and mount visors over the basement.
One of the main problems remains heating. Despite November, heat does not come to all rooms: some batteries are not yet connected to the system, so the gym is not heated. The contractor was instructed to complete the connection of the heating circuit in the coming days.
School No. 33 is at a later stage. The facade is painted, the floors are concreted, the electrical wiring is laid. Now the decoration of the cabinets and the installation of ceilings are continuing. Instead of the three previous heating units, a single heating system was equipped. In addition, the city water utility replaced the worn-out external water supply pipes. The school is scheduled to open after the New Year.
According to the head of administration, the backlog from the schedule is primarily due to the insufficient number of workers. Makarov demanded to immediately increase the composition of the construction crews. The contracts provide for fines for violation of deadlines, and these sanctions intend to apply to contractors.
Major repairs are also ongoing in Bryansk schools No. 32 and 54.