Construction of the overpass in the area of Kolesnikov-Timiryazev street completed by 80-85%
Gradually, the construction of an overpass through the railway in the area of Kolesnikov Street - Timiryazev is being completed. The degree of readiness of the object is 80-85%. About.

Gradually, the construction of an overpass through the railway in the area of Kolesnikov Street - Timiryazev is being completed. The degree of readiness of the object is 80-85%. This became known on October 13 during a visiting meeting on the construction site under the leadership of the Chairman of the Minsk City Executive Committee Vladimir Kukharev, reports the correspondent of the agency “Minsk-Novosti”.
The construction will connect Frunze and Central, which will make communication between the districts much more convenient. Now, in order to get from Masyukovshchina, Stone Hill and Dombrovka to Lebyazhy or the Zhdanovichi market, you have to make an impressive hook along the second transport ring or go to the Moscow Ring Road.
According to the director of the branch of MSU No. 2 "Mostostroy" Sergey Rubcheny, the object is laborious, but already typical - folds up as a designer. Such structures in recent years often have to deal with.


- As for the technical characteristics, the design of the overpass, the length of which will be 381 m, includes 13 supports and 12 span buildings (11 of them with beams of 33 m and another 18 m). The width varies from 41.3 to 47.8 m. On the main section of the building will be provided six-lane movement - three in each direction. At the entrance to the street. The number of strips in both directions will increase from three to five. This technological solution is due to the need to arrange convenient left and right-turn congresses at intersections. By the way, the congresses themselves are fully ready, said S. Rubchen. - Now waterproofing is being laid on the mounted and concreted sections of the bridge. Then we will deal with the leveling and protective layers of asphalt concrete. Almost all materials used are Belarusian, including reinforcement and concrete.




The readiness of the facility is 80-85% and is growing daily.
- It remains to mount the last span structure, the work is planned to be completed by October 20. In parallel, we will proceed to the monolodication of joints and beams in the span, the installation of the final deformation seam. We plan to finish this by November 10. By the same time, we want to complete the installation of the remaining beams on the sidewalks with their parallel monolithization. I note that for pedestrians on both sides there are stepless ramps, sidewalks (one of them will be combined with a bicycle path). We expect to start laying the final layers of asphalt concrete pavement of the roadway and covering pedestrian areas after November 10, added Sergey Panev, director of Gordorstroy. Of course, preliminary dates are given. Much will depend on the weather and temperature. However, we will continue to work strictly within the framework of existing regulatory documents and technological standards.

After the installation of all layers of asphalt concrete coating, specialists will test the overpass with a load to obtain an official protocol on the reliability of the technical structure.
S. Panev added: by mid-November, it is planned to complete the improvement at the facility itself, in parallel, order will be restored under it and in the adjacent territories. By the way, under the construction (in the area of Kolesnikov Perimeter) it is planned to organize a temporary interception parking for vehicles.


- We expect to fulfill all the main tasks in 2026, said the director of Gordorstroy. By 2027, only those that are strictly tied to favorable weather conditions, for example, painting, plastering, will remain.
Every day the facility employs from 45 to 150 people, depending on the specifics of the work performed.

Bridge workers, whose tasks are directly related to the construction of overpass structures, work around the clock. As for improvement, the process is organized in an extended mode, but without weekends, Panev added. The facility was built quickly, ahead of the regulatory deadlines. Of course, first of all, this was possible thanks to our builders, their skill and professionalism. The 24/7 schedule significantly reduced construction time without loss of quality.

Next, more
The Chairman of the Minsk City Executive Committee stressed that the overpass through the railway near Kolesnikova and Timiryazev Street is part of a global project to develop the transport infrastructure of the capital. In particular, we are talking about the formation of the so-called third transport ring.
The task for the coming years is to implement this concept. Today, Minsk is developing at a rapid pace. The number of cars is increasing, which means that it is necessary to modernize the relevant infrastructure, Kukharev explained.

After putting the structure on the street. Kolesnikova and Timiryazev next major object will be the extension of the street. Čiurlionis (a section from Ciurlionis Street to Korzhenevsky Street). This large-scale project is associated with the reconstruction of part of the streets, including the site in the market area near the 11th city clinical hospital. In addition, in 2027, they plan to begin the construction of an overpass over the railway - from the street. Svislochskaya to Selitsky Street. The task of specialists is to build it as soon as possible.

The issue of modernization of production capacities of enterprises that produce beams of span buildings is also being considered.
- The successful implementation of such projects is the merit of our builders. It was their professionalism that became the key force without which it would be impossible to implement these and other large-scale plans, the Chairman of the Minsk City Executive Committee concluded.