The court in Sudogda recovered from the contractor more than 5 million rubles for the unfinished house
By August 2026, the work was never fully completed.

The Sudogodsky District Court considered the case of violation of the terms of the construction contract. The individual entrepreneur undertook to build a residential house, but did not fulfill his obligations on time. As a result, more than 5 million rubles were recovered from him.
According to the case materials, the contract for the construction of an individual residential building was concluded in October 2023. The cost of the works amounted to 6 million 190 thousand rubles, they were planned to be completed by July 1, 2024. Later, the parties signed an additional agreement, postponing the completion of work to May 2026. Payment was at the expense of credit funds in the amount of 4 million 451 thousand rubles and maternity capital for 561 thousand rubles.
By August 2026, the work was never fully completed. The unfinished house was estimated at 3 million 636 thousand rubles. The plaintiff demanded to return the difference between the paid amount and the actual amount of work, which amounted to 1 million 376 thousand rubles. In addition, he asked for a penalty, losses in the form of interest on the loan, compensation for moral damage and a fine of 50 percent of the amount recovered.
The court sided with the plaintiff. The contract was terminated. From the entrepreneur recovered 1 million 376 thousand rubles received under the contract, a penalty in the same amount, losses on credit interest in the amount of 719 thousand rubles, a fine of 1 million 745 thousand rubles and 20 thousand rubles as compensation for moral damage. Also, the defendant must pay a state fee in the amount of 51 thousand 300 rubles to the budget.
The court decision has not yet entered into force.