Technical passage on the Myasnoryadsky bridge in Vologda will open before the end of the year
In the regional capital, two contractors are engaged in the repair of the Myasnoryadsky bridge

In the regional capital, two contractors are engaged in the repair of the Myasnoryadsky bridge. Before the deadline for two months completed the reconstruction of domestic sewerage. The project took six months to do that. The workers managed in four months.
At the moment, communication networks have been removed, the water supply has been reconstructed. Next week, sewers will be put on the new route. Soon, bridge builders will begin to concrete the cone and mount the beams of the span structure.
The head of Vologda Sergey Zhestyannikov said that the technical passage and passage for pedestrians is planned to open before the end of the year. Next year, the final works and improvement of the territory will take place.