Learn how the modernization of the 11th city children's clinic of Minsk is progressing
The progress of modernization of the 11th city children's polyclinic of Minsk was inspected by the Chairman of the Health Committee of the Minsk City Executive Committee Yuri Gorbich and the head of the Ministry of Health.

The progress of modernization of the 11th city children's polyclinic of Minsk was inspected by the chairman of the health committee of the Minsk City Executive Committee Yuri Gorbich and the head of the administration of the Pervomaysky district Alexander Dragun. This sb.by reported in the health Committee of the Minsk City Executive Committee.

The discussion was attended by representatives of the customer - UE "Medic", general contractors - UE "Trest Minskpromstroy" and LLC "Makanstroy", project organization - OJSC "Institute Belgosproekt".
The readiness of the facility, the quality of tasks and compliance with schedules were considered. The task is to accelerate the pace of work: the clinic should open as soon as possible.
Much has been done. Completely completed installation of external engineering networks, at the finish line - finishing the facade and roofing. The installation of heat, electricity and water supply systems inside the building is completed. On the technical floor, a thermal point and a water measuring unit are mounted. Cleaning is actively carried out in the premises.