We learned how the construction of an infectious disease hospital on the Dolginovsky tract is progressing in Minsk
In Minsk, the construction of an infectious disease hospital on the Dolginovsky tract continues. Ready to finish the case of especially dangerous infections and hozblock, at the finish of the ward ...

In Minsk, the construction of an infectious disease hospital on the Dolginovsky tract continues. Ready to finish the case of especially dangerous infections and hozblock, at the finish of the chamber building, and the main forces of the finishers are focused on the main building. This was reported by sb.by in GPO Minskstroy.

The facility currently employs about 500 people, including 150 SU-211 finishers. As for the construction and installation work, a significant amount has already been completed. In the case of especially dangerous infections and hozblock receives equipment, completed engineering facilities.
- At the finish, the chamber buildings: the clean finish is completed, medical consoles of therapeutic gases, electrics are mounted, sanitary dishes are installed, commissioning of engineering systems is carried out, the association said. - They're already bringing furniture into the boxes. In all four "tent rooms" mounted bypass galleries and pneumatic mail, later they will be associated with the main building.
The main forces of the finishers are now concentrated on the main building. In September, the builders plan to finish the facade. The hull is divided into 7 blocks. Inside are already painted, tiled, mount partitions, install doors. The largest volumes of finishing work were performed in five blocks out of seven.
On the territory of a wide front work on improvement is carried out. Pavement slabs are laid, passages are paved, lawns are formed. The overall readiness of this stage is about 70 per cent.
In September, it is planned to complete the installation of the fencing of the entire complex, several sections remain to be installed. The length of the fence is 4 kilometers. Entrance gates and wickets are also installed, spacious guest parking is equipped.
The pace of work remains high, the builders work without days off. By the end of the year, about 50 thousand square meters of rental housing will be put into operation in Minsk