In the Genic district checked the repaired road to the station Novoalekseevka
In the Genic municipal district, the quality of the overhaul of the highway with a length of more than two kilometers connecting the Federal highway R-280 "Novorossia" and the railway station Novoalekseevka was checked

In the Genic municipal district, the quality of the overhaul of the highway with a length of more than two kilometers connecting the Federal highway R-280 "Novorossia" and the railway station Novoalekseevka was checked. This was told in the story of the Tavria TRK.
Traffic on the site was opened in the spring, but now it is checked by construction audit specialists. Engineers used the road wheel to measure the geometric parameters of the track and compared them with the design documentation. They also conducted laboratory tests of samples of crushed stone and asphalt concrete mixture.
Director of the road construction company Alexei Moiseev said that each stage of construction is controlled by internal specialists and the customer. The track is designed for more than 10 years of operation, and warranty obligations are valid for three years.
Two layers of asphalt were laid on the site and road signs were installed. The working commission identified shortcomings: the lack of permanent road markings and uncut grass on the roadsides. The contractor was given 10 days to remove the comments.
Deputy Head of the Road Management Department of the Ministry of Transport of the Kherson region Roman Ramazanov explained that the working commission checks the condition of the carriageway, the quality of the work performed, the geometry of the road and the correctness of the installation of technical means of road traffic management.
After the removal of all comments and the signing of the acceptance certificate, the updated road will be officially transferred to the regional ownership.