In the Ivanovo region laid more than two kilometers of pipes for a new collector
According to specialists of the Federal Center for Construction Control, the dynamics of work is good, people and equipment are more than provided for by the schedule of work
According to specialists of the Federal Center for Construction Control, the dynamics of work is good, there are more people and equipment than envisaged by the schedule of work.
Currently, the contractor has laid more than 2.1 kilometers of the highway and installed 13 wells. The construction covers four points, one of them is preparing a base for drilling a duker crossing through the Black River. These works involve 38 workers and 19 units of special equipment, including cars for pumping drilling sludge, pumping and mixing plants and cranes-manipulators.
The project is being implemented within the framework of the federal project “Water of Russia”, involving the laying of a main collector with a length of 27 and a half kilometers and the launch of eight pumping stations. The new manifold will combine Kineshma and Navoloki, where ten separate treatment plants are currently operating with 85 percent depreciation.