In the boiler houses of the Babaev district updated equipment for the heating season
In the Babaevsky district, by the beginning of the heating season, seven boilers were replaced in the municipal boiler houses of the village of Borisovo-Sudskoye and the villages of Pozhara and Saninskaya

In the Babaev district, by the beginning of the heating season, seven boilers were replaced in the municipal boiler houses of the village of Borisovo-Sudskoye and the villages of Fire and Saninskaya.
The work was carried out under the state program for the development of fuel and energy complex and municipal infrastructure with the support of the Governor. Funds are allocated from the regional budget. The district’s boiler houses also updated 12 safety valves, 12 network pumps and two control cabinets for pump groups, and gasoline generators were purchased for two boiler houses.
Improvements in the communal sphere will be felt by more than six hundred residents of settlements of the municipality. The heating season here started in normal mode.