In “Minskenergo” called the cause of the heat outage in 20 houses of Pervomaysky district
Heat supply was suspended for scheduled repair of the network section identified during regular monitoring.

Minskenergo explained the reason for the temporary shutdown of hot water supply and heating in more than 20 residential buildings of Pervomaysky district of Minsk.
According to Andrey Zheshko, First Deputy Director and Chief Engineer of the Minsk Heat Networks branch, damage to the pipeline was revealed several weeks ago during regular monitoring. Since then, the site has been under constant supervision of specialists.
“This approach allows you to prevent the development of the defect to the emergency stage and plan recovery measures in advance,” said the engineer.
In this regard, yesterday a site for repairs was prepared, about which residents were warned in advance. Today, the work was carried out in a planned manner and in strict accordance with the regulations. At the time of repair, consumers remained without heat and hot water on the streets of Academic, Surganov, Volgograd and Independence Avenue.
By 14:00, the damage was repaired, and at 15:30 the heating system was filled, and the parameters were adjusted to the specified mode. At present, the connection of consumers to resources is being completed.
Photo: BELTA