In Volga, the developer will pay for the delay of the apartment
In the Volga district court considered a civil case on the claim of a resident of the city of Ples to the developer

In the Volga district court considered a civil case on the claim of a resident of the city of Ples to the developer. The woman demanded a penalty for the delay in the transfer of an apartment in Moscow.
In September 2025, the plaintiff purchased real estate worth 7.3 million rubles, using personal savings, credit and maternity capital. However, the company violated the terms of the contract, handing over the keys 164 days later than the deadline.
The buyer asked to recover more than 6 million rubles of penalties, compensation for moral damage and a fine.
The court partially granted the claim, reducing the amount of the penalty as clearly disproportionate to the consequences. As a result, 700,000 rubles of penalty, 60,000 rubles of compensation for moral damage and 100,000 rubles of fine for refusal to voluntarily satisfy the requirements were recovered from the developer.
The court decision has not entered into legal force.