In Tambov inspected the construction of the road on the street Magistralny in the neighborhood “Volzhsky”
In Tambov, an on-site working meeting was held dedicated to the progress of work at the facility “Construction of a highway along the street”

In Tambov, a visiting working meeting was held on the progress of work at the facility "Construction of a highway on Volzhskaya Street on the site from the street." Caucasian to the street. Main (2nd stage)”.
The event was attended by acting Deputy Minister Svyatoslav Erokhin, representatives of TOGBU "Unified Customer Service" headed by Director Ramil Tliy, specialists of FBU "ROSTROYCONTROL", as well as representatives of the contractor organization "Real-Max" and LLC "GK-Project".
During the trip, the participants assessed the amount of work performed. As of early November, the facility is working on the arrangement of the land, parallel pavement of sidewalks and construction of water supply. Fully completed reclamation, restoration and consolidation of the track.
Construction is carried out within the framework of the national project “Infrastructure for Life”. The length of the projected section of Magistralnaya Street from Bastionnaya to Kikvidze is about 1.2 kilometers. The number of lanes is 4, the design speed is 70 km / h, the width of the sidewalk is 3 meters.
The new road will directly connect the two districts of the western part of Tambov and pass through the territory allocated for integrated development. The Volga district is developing comprehensively: in addition to the road, residential buildings, a school for 1,275 children and two kindergartens are being built here.