In Vasilievskoye completed the installation of a modern water treatment station
In the village of Vasilievskoye, the installation of a new water treatment station is coming to an end

The work is carried out within the framework of the investment program of MUP “Vodokanal-ботService”. The capacity of the new station is 17 cubic meters per hour. It is important for residents that at the time of installation, the water supply to the houses was not turned off for a day.
- We understand that any interruption is critical for residents, so we put the station into operation in stages, without stopping the water supply. Now the commissioning is underway: we are reconfiguring the equipment so that it works clearly and without failures, commented the head of the district Alexei Shimko.
Previously, the station had only deiron filters. They couldn't handle fluoride. The new system includes several cleaning steps.
- At the entrance is a mesh filter that cuts off sand and rough inclusions. The aerator is then a device that converts trivalent iron into bivalent iron so that it can be deposited. Then there is a de-ironing system, where precipitation occurs, explained the director of the contractor Vikenty Makarov.
According to the head of the water pumping station Lyudmila Merkulova, the main task is to bring the water parameters back to normal.
Iron precipitated, its presence in the water was visible, and fluoride is visually invisible, but, nevertheless, its excess is not very good for health. Now the water will meet all the requirements of SanPiN, she said.
The commissioning work is scheduled to be completed in November. Next year, a similar station will be built at a water intake hub in the village of Sharapova Okhota, and the modernization of water intake hubs in Pushchino will continue. For the village of Vasilievskoye, the new station is not just a replacement of equipment, but a solution to a problem that residents have faced for years.