The authorities told about the construction of water supply networks for the interuniversity campus in Orel
On the progress in the construction of water supply networks necessary to ensure the interuniversity campus under construction of the FSBEU VO Orel State University

The progress in the construction of water supply networks necessary to provide the interuniversity campus of the I.S. Turgenev Orel State University with water supply was told in the regional Department of Road Management in their group in the VKontakte social network.
As explained in the department, to provide water supply to the objects of the student campus, water supply networks are being built in the area of the Naugor highway in the Soviet district of the city. The work is carried out by the contracting organization of LLC "PSK Neftegazmontazh". Funds for this purpose were allocated and the treasury of the region.
The contract provides for the construction of two stages. The first stage is the ring water supply network from Tsvetaev Street along the Heroes of the Fire, Kartukov Street, Skvortsov Street, Naugorskoe Highway. The second stage is water supply networks from Skvortsov Street along the Naugorsk highway, Surnev Street, General Gorbatov Street, Donetsk Street, Lugansk Lane. The total length of the networks will be 6.6 km: 2.6 km in the first stage and 4 km in the second.
According to FBU "Rosstroycontrol", carrying out construction control at the facility, the construction readiness of the facility is currently 88%.
To date, the first stage of laying water supply networks is 100% completed. Work is being carried out on the improvement of the territory, compensation planting of trees, restoration of the road surface. In the second stage, work is underway on the development of soil, laying pipelines and backfilling with sealing. More than 75% of water pipes are laid.
Completion of construction and commissioning of the facility is planned before the end of 2026.