Western bypass of the Eagle for the second time in a month reduced the cost of construction
Western bypass of the Eagle for the second time in a month reduced the cost of construction

The western bypass of the Eagle reduced the cost of construction for the second time in a month. According to the publication “InfoOrel”, at the end of September 2026, the contract fell by almost 73 million rubles, although the terms of work have not changed. Currently, less than 43% of the funds have been spent, which raises questions about the real progress of work and the volume of construction.
Experts and MPs hope to understand what works are really carried out and whether it will affect the quality and timing of the road.
Earlier, “MK in Orel” wrote that in April 2026, the work had to be suspended, because because of the flood washed away the access roads and on-site, the equipment of the contractor could not enter the facility. In July, the governor of the Orel region said that the issues with federal funding were resolved, the money came, the contractor returned.