The heat grid left and did not fix the drawdown of tiles on Zakharyevskaya after the accident
GATI announced a warning to JSC Heat Grid of St. Petersburg, the general director of which is Vadim Bravve. The reason was the failure to fulfill the obligation to eliminate the drawdown and swelling of the tiled pavement of the sidewalk on Zakharyevskaya Street, 25. This became known from the data of the Prosecutor General of the Russian Federation.

GATI announced a warning to JSC Heat Grid of St. Petersburg, the general director of which is Vadim Bravve. The reason was the failure to fulfill the obligation to eliminate the drawdown and swelling of the tiled pavement of the sidewalk on Zakharyevskaya Street, 25. This became known from the data of the Prosecutor General of the Russian Federation.
The defect was formed after emergency work on the notification of August 12, 2026. As reported in the inspection, on September 10, specialists of the SPb GBU “Central Directorate of Regional Roads and Improvement” recorded a drawdown of tiles in the zone of the warranty pit.
The Heat Grid received a notification on the need to eliminate the defect on September 17, but by September 30, the work was not performed. According to the rules of improvement, the elimination of such defects is given no more than 10 days from the date of notification.
GATI demanded that the organization put the pavement in order. According to Kontur.Focus, JSC Heat Grid of St. Petersburg is the defendant in 20 cases totaling 49 million rubles.