Anapa is building a 20-kilometer water pipeline: work is planned to be completed in 2028
In Anapa, the construction of a water conduit with a diameter of 900 mm from water intake treatment facilities to clean water tanks in the village of Upper Dzhemete continues

In Anapa, the construction of a water conduit with a diameter of 900 mm from water intake treatment facilities to clean water tanks in the village of Upper Dzhemete continues. The design length of the structure is about 20 km, said the head of the city Svetlana Maslova.
According to the mayor, the new water pipeline will increase the capacity of water supply networks by 50 thousand cubic meters per day. This will provide high-quality water Utash, Grape, Vityazevo, Cibanobalka, Red Kurgan, Resurrection and other settlements. The project should also contribute to the further development of the municipality.
Now about 100 people and 10 units of equipment are involved in the construction. The workers developed 2,790 linear meters of the trench and laid 1,668 linear meters of the pipeline. Concrete preparation, reinforcement of switching chambers and formation of punctures under roadways are also continuing.
Archaeological fieldwork is carried out on three sections of the water duct route. The progress of construction is controlled by Deputy head of Anapa Vitaly Lazutchenko. The project is scheduled to be completed in June 2028.
Earlier it was reported that in the village near Anapa set a swing, a carousel and a game complex.