In Arkhangelsk continues the overhaul of the hostel pedagogical college
23 specialists work on the site daily, the total construction readiness of the facility is 83%

23 specialists work on the site daily, the total construction readiness of the facility is 83%. According to the Minister of Construction and Architecture of the Arkhangelsk region Vladimir Polezhayev, work on the installation of power supply networks is nearing completion - they are 90% ready. In parallel, the contractor continues the construction of floors (readiness 85%) and walls (84%). The finishing stage is still in the initial stage: readiness is 21%, which corresponds to the approved plan. The final finishing works will begin after the completion of the main construction and engineering works.